Tooga Theatre Renovation Bid on Hold Pending $1M ARC Approval
Chattooga County is waiting on Appalachian Regional Commission approval before awarding the Tooga Theatre renovation contract, after all four phase-one bids came in above available funding.

Programme
- The apparent low bid is $1,451,503 from The Mitchell Group LLC of Carrollton; bids opened October 27.
- All four phase-one bids exceeded available funding, from $1,451,503 to $1,858,000.
- The commission has committed $1 million, and the county identified about $200,000 in unrestricted local funds for matching.
- Phase one covers interior demolition, rear-building improvements, ticket booth and front entrance work, audiovisual equipment and furnishings.
- Allen gave no timetable for commission approval or the naming of a contractor.
By Elena Vasquez
Chattooga County has not awarded the Tooga Theatre renovation contract, and the apparent low bid of $1,451,503 now waits on Appalachian Regional Commission approval. County Sole Commissioner Andy Allen told WZQZ News this week that the county needs the commission's go-ahead before it can move forward with awarding the contract. The bids were opened on October 27 after several weeks of proposal review and cost-cutting work.
What do the four bids show?
Four contractors submitted bids for the first phase of the renovation, and every proposal exceeded the funding initially available. The Mitchell Group LLC of Carrollton holds the apparent low bid at $1,451,503.
- The Mitchell Group LLC, Carrollton — $1,451,503, apparent low bid
- Headley Construction Corporation, Newnan — $1,682,674
- J.K. Lockwood Construction, Alpharetta — $1,691,000
- Banner Services Group LLC, Canton — $1,858,000
The spread between the lowest and highest bids is $406,497, roughly 28 percent of the low figure. The four proposals average about $1.67 million each, about $670,000 more than the $1 million the commission has committed to the project.
How does the funding line up?
The commission has committed $1 million in Appalachian Regional Commission funding, and Chattooga County must supply local matching funds. The county previously identified approximately $200,000 in unrestricted local funds available for the project — one-fifth of the grant amount.
Against the low bid, that leaves a gap of $451,503, about 45 percent of the $1 million commission contribution. The identified local money covers roughly 14 percent of the apparent low bid, which means about $251,503 remains to be found unless negotiations reduce the price or other money appears.
Why is the county still negotiating?
Allen told WZQZ News earlier this month that he was negotiating with one of the low bidders to bring construction costs down before awarding a contract. The county has also been reviewing the proposals to identify possible savings while preserving the essential work needed to restore the building.
That review has run for several weeks, and it continues while the county waits. Allen said the county still needs to hear from the commission before it awards the work.
What does the first phase cover?
Phase one concentrates on the theatre's interior. The scope includes demolition, improvements to the rear portion of the building, renovations to the ticket booth and front entrance, and installation of audiovisual equipment, furnishings and other fixtures.
Why is the theatre still not ready for the public?
The county-owned Tooga Theatre stands on Commerce Street in downtown Summerville and has been the focus of restoration efforts for several years. Earlier work covered the building's exterior and marquee. Significant interior renovation remains necessary before the facility can return to regular public use, and none of it can start until a contract is awarded.
When will the contractor be named?
Allen provided no timetable for receiving commission approval or for announcing the contractor who will perform the work. The current update confirms only that no construction contract has been awarded. WZQZ News will continue following the project as the county awaits the approval needed to proceed with the renovation.
Until the commission signs off and the county closes the $451,503 gap between the low bid and its available funding, the Tooga Theatre cannot return to regular public use.